Order to halt Riveli Restaurant eviction voided

Civil Court interim order to halt a notice seeking to terminate the agreement between the Housing Development Corporation (HDC) and Solaris Hospitality Private Limited over the plot housing Riveli Beach Club and Restaurant, as well as a directive to suspend all business operations over prolonged unpaid rent to HDC has been voided.

Featured Image

[File] Riveli Beach Club and Restaurant decorated for a wedding event

Umar Shan Shafeeq

2026-11-18 13:31:31

The interim order issued by the Civil Court to halt a notice seeking to terminate the agreement between the Housing Development Corporation (HDC) and Solaris Hospitality Private Limited over prolonged failure to pay rent to HDC for the plot housing Riveli Beach Club and Restaurant, as well as a directive to suspend all business operations has been voided.

HDC sent a letter to Solaris last month, informing the company that they were voiding the commercial agreement made with them and that they had reclaimed the plot.

Following the notice, HDC entered the Riveli premises to evict the operator. However, Solaris filed a case with the Civil Court challenging the eviction, seeking to overturn HDC's decision and obtain an interim order preventing HDC from vacating the premises.

Although the Civil Court initially rejected the request, they later issued an interim order. 

Civil Court directed that HDC must not take any action to halt operations at Riveli and, if any such action has already been taken, must restore the premises to their previous state.

HDC requested the Civil Court to review the order, with the court ruling to void the order today. The ruling regarding the review of the order from the Civil Court reads that due to the interim order that was issued while the defendant was absent is sustained, HDC has to bear an unfair burden.

The ruling states the losses that may be incurred while the case remains to be decided may not be predicted at this time, and so maintaining the order would not be just.

The Civil Court highlighted that the court had ruled against the interim order that was requested along with the form to file the case, and even though the ruling was appealed at the High Court, no decision has been reached yet.

The court also said there have been no changes in circumstance since the initial ruling against the first interim order request.

The Civil Court's ruling reads that there is a complete arrangement where Solaris will be financially compensated for any losses should it be proven in trial that the notice was issued in violation of the agreement.

And so, the court reviewed the interim order and ruled to void it from today onward.

HDC said its agreement with Solaris was terminated due to long-overdue rental payments, adding that the decision was made in accordance with the agreement's procedures after the company had been issued multiple notices and given opportunities to settle the outstanding rent.

An official from HDC stated that Solaris, the company managing the restaurant at the Ruhgandu 1 area in Hulhumale', owes approximately MVR 5 million to the corporation to date. The official also said rent has not been paid regularly after the agreement was made and that even after letters were sent, only a portion of the rent was paid.

According to the official, none of the required CSR initiatives have been carried out either.

The issue of parties failing to regularly pay rent owed to HDC has escalated, with complaints raised over a prolonged period of time. This includes rent for certain businesses as well as flats.