Hulhumalé Phase 3 reclamation resumes after halt

The project, which was contracted to Capital Marine and Civil Construction (CMC), involves the reclamation of a total of 63 hectares of land, according to the government’s plan.

Featured Image

HULHUMALE PHASE 3 RECLAMATION

Shazma Thaufeeq

2025-11-10 20:00:30

The land reclamation project for Hulhumalé Phase 3, which aims to alleviate the severe housing crisis in the Malé region, has restarted today after a temporary suspension.

Following the resumption of the remaining 38 hectares of reclamation work for Hulhumalé Phase 3, President Dr. Mohamed Muizzu visited the area today to inspect the progress and gather information on the ongoing work.

The project, which was contracted to Capital Marine and Civil Construction (CMC), involves the reclamation of a total of 63 hectares of land, according to the government’s plan.

President Dr. Muizzu observing the resumed reclamation work of Hulhumalé Phase III this afternoon. --- Photo: President's Office

The Ministry of Construction stated that since the project began in September 2023, 24 hectares of land had been reclaimed prior to the halt. The Ministry explained that the project was paused due to the commencement of the work to revise the Hulhumalé Master Plan.

President Dr. Muizzu observing the resumed reclamation work of Hulhumalé Phase III this afternoon. --- Photo: President's Office

Housing Development Corporation issued a notice requesting that all marine vessels traveling near the Hulhumalé Phase III area exercise caution due to the restart of the reclamation work.

The Ministry of Construction confirmed that the government is working to complete the project swiftly to maximize housing opportunities for citizens.