Thilamalé Bridge works updates shown

Malé - May 6, 2026: An event was held to show the progress of the Thilamalé Bridge to journalists. Minister Dr. Abdulla Muththalib and Indian High Commissioner Munu Mahawar (Bala Subramaniam) participated in this event. Currently, the main work on-site involves casting and installing the segments required for the bridge deck. Out of the total 1,222 segments needed for the bridge deck, 86 percent have already been cast. The Thilamalé Bridge is a USD 500 million (MVR 7.7 billion) project. --- Photos: Fayaz Moosa | Mihaaru

Work ongoing for the Thilamalé Bridge, which will connect Malé, Villimalé, Gulhifalhu, and Thilafushi -- Photo: Fayaz Moosa | Mihaaru

Thilamalé Bridge: A major part of this massive project, which will reduce the current six-minute sea ferry journey between Malé and Villimalé to approximately one minute, has now been finished. --- Photo: Fayaz Moosa | Mihaaru

The area where work is progressing on the Villimalé intersection of the Thilamalé Bridge -- Photo: Fayaz Moosa | Mihaaru

Employees of Afcons, the company constructing the Thilamalé Bridge, at work: 60 percent of the segments have already been installed. --- Photo: Fayaz Moosa | Mihaaru

Minister Muththalib and Indian High Commissioner Munu Mahawar (Bala Subramaniam) observe the work on the Thilamalé Bridge connecting Malé, Villimalé, Gulhifalhu, and Thilafushi: A large portion of the bridge work is complete. --- Photo: Fayaz Moosa | Mihaaru

Afcons employees working on the bridge: 72 percent of the total project is now finished. --- Photo: Fayaz Moosa | Mihaaru

Afcons employees carrying out work on the bridge: The Thilamalé Bridge is a USD 500 million (MVR 7.7 billion) project. --- Photo: Fayaz Moosa | Mihaaru

Afcons workers at the Thilamalé Bridge site: A large part of the bridge work has been completed. --- Photo: Fayaz Moosa | Mihaaru

The Villimalé intersection of the Thilamalé Bridge: A significant portion of the bridge work is now finished. --- Photo: Fayaz Moosa | Mihaaru

Thilamalé Bridge: The primary focus on-site currently is the casting and installation of the segments required for the bridge deck. --- Photo: Fayaz Moosa | Mihaaru

Minister Muththalib and Indian High Commissioner Munu Mahawar (Bala Subramaniam) inspecting the work on the bridge connecting the four islands. --- Photo: Fayaz Moosa | Mihaaru

Afcons workers engaged in the Thilamalé Bridge project: Much of the bridge construction is complete. --- Photo: Fayaz Moosa | Mihaaru

Afcons workers at the bridge site: A large portion of the work is now finished. --- Photo: Fayaz Moosa | Mihaaru

Thilamalé Bridge: This grand project will shorten the transit between Malé and Villimalé to a mere minute; most of it is now done. --- Photo: Fayaz Moosa | Mihaaru

Work continues on the Thilamalé Bridge: 86 percent of the total 1,222 segments required for the deck have been cast. --- Photo: Fayaz Moosa | Mihaaru