Maldives Transport and Contracting Company (MTCC) said the harbor development project of Hulhudhoo, located on the northeastern point of Addu City, is 90 percent complete.
According to, MTCC the the company carrying out the project, construction of pavements and installation of street lights in the harbor area has been completed.
Under the project, 742 meters of quay wall construction and 624 meters of revetment in addition to 88,623 cubic meters of land reclamation were carried out.
The project worth MVR 66.3 million was contracted to MTCC by the Planning Ministry.